When are Evaluations Conducted?

Article
Read time: 6 minutes

C.G.S. 4a-101 states that once my company is awarded a project that is subject to the contractor prequalification program, it will be evaluated by the awarding authority or owner. At what points during the project will these evaluations be conducted?


When 50% of the work on the construction project is completed, the awarding authority or owner must give the contractor a written copy of the preliminary evaluation. This 50% evaluation is between the awarding authority/owner and the contractor. DAS does not receive a copy of this evaluation.


When 100% of the work on the construction project is completed, the awarding authority or owner must complete and submit an evaluation form for the contractor (who signed a contract directly with the awarding authority or owner). DAS must receive a copy of this evaluation. This evaluation will factor into the contractor’s ability to prequalify in the future.


NOTE: This evaluation requirement applies only to contractors who have signed a contract directly with the awarding authority or owner.


Contractor Prequalification